Widening Umm Suqeim Road project

0
1381

Source:  www.rta.ae

The Board of Directors of the Roads & Transport Authority (RTA) has endorsed, in a meeting chaired by H.E. Mattar Al Tayer, Chairman of the Board and Executive Director of the RTA, the awarding of a contract for widening & improvement of Umm Suqeim Road, stretching from Sheikh Zayed Road up to Al Khail Road.

The Project has been awarded at a time where construction works in flyovers at the intersection of Al Khail Road & Umm Suqeim Road are nearing completion.

“The project aims at separating the traffic movement crossing from Sheikh Zayed Road to Al Khail Road from the local traffic movement through constructing flyovers at the intersections of this corridor with the Eastern Parallel Road (Al Asayel Road), and the Western Parallel Road (Al Khail Road 1).

Two flyovers will be constructed at each intersection; each flyover consists of 3 lanes in each direction. Two more signalized junctions will be made at the intersection with Al Asayel Road and Al Khail Road, to ensure free traffic movement in all directions,” said Al Tayer.

“Service roads and car parks will be constructed at the frontage of business outlets on both roadsides to serve showrooms at Al Barsha and Al Qouz Industrial Areas. The Project will also step up the safety levels, thanks to the provision of three bridges, pavements, and two signalized pedestrian crossings, in addition to essential services such as street lighting and rainwater drainage.

“Widening & Improvement of Al Al Khail Road Project, at a cost of 1.925 billion dirham, is considered one of the biggest projects currently undertaken by the RTA, and due to the massive nature of the Project, RTA divided it into four phases. The importance of the Project is underlined by its nature as an extension of the Business Bay Crossing, and its role in realizing RTA’s endeavours to open up auxiliary traffic corridors to Sheikh Zayed Road and Emirates Road; as these two roads account for a huge portion of the high traffic volumes.

“Construction works in the Project have reached concluding stages and all key flyovers at the interchanges of the Project are set for opening by the end of this year, while the remaining subsidiary bridges are set for completion in the first half of 2013. Works in some interchanges are nearing completion with completion rates ranging from 72 to 96%. Phase I of the Project, costing about 575 million dirham, aims at easing the traffic flow in the direction from Al Khail Road towards Emirates Road and vice versa, besides ensuring the smooth traffic flow in the property development projects in the area.

“Completion rate in Phase I of the Project, constructed by Emirates Roads Constructing Co., has exceeded 95%, encompassing the construction of a new bridge to replace the circular surface intersection on Emirates Road, thus enabling free traffic movement in all directions.  It also includes the construction of two flyovers; the first links the Emirates Road in the direction of Al Khail Road, and the second links Al Khail Road in the direction of Emirates Road. The Project also comprises increasing the number of lanes from four to six in each direction of Emirates Road and Al Khail Road, in addition to traffic signaling, signage and other utility works,” added Al Tayer.

The RTA opened in September 2011 the Widening of Emirates Road Project, and last April it opened circular slip roads branching out of bridges serving the traffic from Al Khail Road to Dubai, and from Abu Dhabi to Al Khail Road. By the end of December 2012, all remaining phases of the project will be completed.

Phase II of the Project, costing about 762 million dirham and undertaken by Gunal & Mapa Construction Co., comprises the construction of two new flyovers on Al Khail Road to ensure a smooth traffic flow in all directions to replace the existing two R/As at the intersection of Al Khail Road with Street 319 and Street 323 at Al Qouz residential & industrial Areas. It also includes the widening of Al Khail Road from four to six lanes in each direction, and the construction of an elevated link road inbound from Al Qouz and outbound to Al Khail Road; where construction works are currently underway. The Project also includes various road works such as pavements, street lighting, light signals, traffic signs and traffic diversions, in addition to the removal of some existing utility services intercepting the project works, and undertaking new utility works required for the project completion.

“In August 2012, the RTA opened the flyover serving the traffic inbound from Al Qouz Industrial and outbound to Al Khail Road in the direction of Dubai and vice-versa. Last July RTA also opened the Interchange No 22 linking Al Khail Road with Al Qouz Residential Area; which contributed to the smooth traffic flow on Al Khail Road, thanks to the widening of lanes from four to six. It also assisted the traffic movement in the roads linked with Al Khail Road, and eased the traffic congestion inbound from Al Qouz in the direction of Al Khail Road through an elevated link of the traffic coming from Al Qouz and heading towards Dubai. It also eased the traffic flow at the junctions with Al Khail Road on the one hand, and Street 323 and Street 319 on the other, besides easing the movement of trucks and heavy machinery at the Interchange No. 19.

“Ascon Contracting Co., undertaking Phase III of Al Khail Road Improvement Project at a cost of 282 million dirham, is about to complete all works pertinent to widening of Al Khail Project from four to six lanes in each direction from the intersection with Umm Suqeim Road up to the intersection with Emirates Road, besides modifying the curves at Intersection No 13.

“Completion rate has exceeded 70% in Phase IV of the Project, costing 307.368 million dirham and undertaken by Wade Adams Construction Co. It comprises replacing the existing roundabout at the intersection of Al Khail Road with Umm Suqeim Road by a free multi-level interchange providing a smooth vehicular traffic movement in all directions. It also encompasses the widening of Al Khail Road from four to six lanes in each direction, and shifting & protecting the public facilities & utilities impacted by the free interchange. Main bridges on Umm Suqeim Road are penciled for opening by the end of this year, and all works in subsidiary bridges are set for completion by the end of March 2013. When completed, The Project will provide smooth access to areas in the vicinity of the Interchange such as Al Barsha, Al Barsha South, and Al Qouz Industrial among others, thus ensures seamless traffic movement in the neighbourhood. More info